Satellite images track 5 years of construction on the Rosso Bridge between Mauritania and Senegal

According to Al Jazeera, satellite imagery from Planet Labs between November 2021 and November 2026 shows that the Rosso Bridge project, costing approximately $100 million, has evolved from a simple dirt path into a near-complete engineering structure over the Senegal River. The bridge, which spans 1,461 meters including access roads, aims to provide a permanent crossing and reduce travel time on the Nouakchott-Dakar corridor. Officials reported that the project was 62% complete as of September 2026, with an expected inauguration in March 2027. The project is co-financed by the African Development Bank, the European Investment Bank, the European Union, and the governments of Mauritania and Senegal.